Topic 28 of 29: Finishing the new home in Cedar Creek

Fri, Apr 26, 2002 (07:10) | Paul Terry Walhus (terry)
We're going to choose from among four or five builders to occupy and finish our house in Cedar Creek. We put out an ad on our website at

http://tvnight.org/cottage

This topic will track our selection process.
3 responses total.

 Topic 28 of 29 [home]: Finishing the new home in Cedar Creek
 Response 1 of 3: Paul Terry Walhus (terry) * Fri, Apr 26, 2002 (07:11) * 42 lines 
 
Our first partial bid came in. From Mike and Heraldo.

job hours cost start finish
framing rough in ? ? ? ?
plumbing 12 276.00 5/1/2002 5/4/2002
3" pvc 200' 8 68.00
2 toilet lines in and 3 280.00
2 bath tubs 185.00
water heater 50 gal 28.00
10 cut valves 45.00
10 supply valves
1st fl elec ruff in 16 5/5/2002 5/7/2002
2nd fl elec ruff in 16 5/8/2002 5/10/2002
1st fl insul 8 749.36 5/11/2002 5/12/2002
2nd fl insul 10 969.00 5/12/2002 5/13/2002
1st fl sheet rock 25 714.00 5/14/2002 5/18/2002
2nd fl sheet rock 29 816.00 5/18/2002 5/21/2002
tape 10 rools 12 30.00
mud 5 boxes 1st fl 12 25.00 5/25/2002 5/26/2002
2nd fl mud 5/26/2002 5/27/2002
paint 1st fl 10 cans 16 150.00 5/28 5/30
paint 2nd fl 15 cans 18 225.00 5/31/2002 6/2/2002
tile 1st fl 55 boxes 16 840.00 6/3/2002 6/5/2002
tile 2nd fl 55 boxes 16 840.00 6/6/2002 6/8/2002
elec trim out 1st fl 16 6/9/1902 6/10/2002
elec trim out 2nd fl 16 6/11/2002 6/12/2002
int trim
ext trim
decks
hvac
misc
249 6,240.36


So we're missing the framing on this bid, but Mike's bringing his framer
Saturday morning to complete the estimate. He only wants one floor but
will finish the whole place in a month and a half. Which would enable us
to rent out one floor. The costs look reasonable. He's showing us an
8,000 square job he did recently where he did all the electric, plumbing
and sheetrock.

We're waiting on four other bids.


 Topic 28 of 29 [home]: Finishing the new home in Cedar Creek
 Response 2 of 3: Paul Terry Walhus (terry) * Fri, Apr 26, 2002 (07:19) * 6 lines 
 
That looks bad.

Here's a better view.

http://tvnight.org/yapp-bin/public/read/home/28



 Topic 28 of 29 [home]: Finishing the new home in Cedar Creek
 Response 3 of 3: Paul Terry Walhus (terry) * Fri, Apr 26, 2002 (07:20) * 4 lines 
 
I meant.

http://tvnight.org/cottage/bidmike.html